Sydney Cricket Ground
A W Edwards
In 2008 Normoyle was successful to win a significant contract at Sydney's prestigious home of cricket- the Sydney Cricket Ground.
Commencing work in August 2008, Normoyle faced the challenging task of fabricating and installing over 2700 meters of custom balustrade and handrail in just under 5 months. With the challenge set, Normoyle stepped immediately into action and by the beginning of December the project was complete in time for the 2008/2009 cricket season.
Comprising of work with stainless steel, galvanized steel and glass, Normoyle utilized their experienced and highly technical team of project managers, engineers and draftsmen to design simple to manufacture and install components that would both provide exceptional levels of safety and enable a low cost, fast installation of the upmost quality.
|
|